On Monday we got the final plans for the house which we had to check and sign. There was only one minor issue with one of the walls - we thought it had been solved first time round. A couple of emails later, and it was. Here is the plan, if you can make head or tail of it:
Note red pen and marker...
The kick-off meeting with all involved (house builders, foundation "layers", digging company, waterworks, electrician, architect, surveyor) takes place some day in the week starting 19th May, the earth-moving has to be finished by 13th June, and the foundations will be laid sometime (takes about a week) between then and 28th June.
Watch this space...